Collapsed Cabagan-Santa Maria bridge just opened Feb 2025, cost P1.2-B - DPWH
Collapsed Cabagan-Santa Maria bridge just opened Feb 2025, cost P1.2-B - DPWH
The Cabagan-Santa Maria Bridge in Isabela, a portion of which collapsed Thursday night, was completed and opened to the public earlier this month, the Department of Public Works and HIghways-Cagayan Valley said Friday.
The Cabagan-Santa Maria Bridge in Isabela, a portion of which collapsed Thursday night, was completed and opened to the public earlier this month, the Department of Public Works and HIghways-Cagayan Valley said Friday.
Total project cost was at P1.225 billion including the bridge and approaches.
Total project cost was at P1.225 billion including the bridge and approaches.
DPWH Cagayan Valley said construction of the bridge, which had a total length of 990m including 12 arch bridges and approaches, started November 2014. It was completed more than 10 years later at Feb. 1, 2025.
DPWH Cagayan Valley said construction of the bridge, which had a total length of 990m including 12 arch bridges and approaches, started November 2014. It was completed more than 10 years later at Feb. 1, 2025.
“The construction of the bridge started on November 2014 and was completed on February 1, 2025 with a total cost of P1,225,537,087.92 (Bridge & Approaches),” the DPWH said in a statement.
“The construction of the bridge started on November 2014 and was completed on February 1, 2025 with a total cost of P1,225,537,087.92 (Bridge & Approaches),” the DPWH said in a statement.
ADVERTISEMENT
“Total length of the bridge is 990m consisting of 12 Arch Bridge with a span of 60m and 9 spans of Pre-Stressed Concrete Girder (PSCG) Type IVB and the total length of approaches is 664.10 ln. m. The contractor of the bridge is R.D. Interior, Jr. Construction,” it added.
“Total length of the bridge is 990m consisting of 12 Arch Bridge with a span of 60m and 9 spans of Pre-Stressed Concrete Girder (PSCG) Type IVB and the total length of approaches is 664.10 ln. m. The contractor of the bridge is R.D. Interior, Jr. Construction,” it added.
It said a 60-meter arch bridge portion of the Cabagan-Santa Maria Bridge collapsed at around 8 p.m. Thursday after a “dump truck carrying boulders with a calculated approximate gross vehicle weight (GVW) of around 102 tons passed on it.”
It said a 60-meter arch bridge portion of the Cabagan-Santa Maria Bridge collapsed at around 8 p.m. Thursday after a “dump truck carrying boulders with a calculated approximate gross vehicle weight (GVW) of around 102 tons passed on it.”
The collapse damaged 4 vehicles including a dump truck, 2 SUVs and a motorcycle.
The collapse damaged 4 vehicles including a dump truck, 2 SUVs and a motorcycle.
“Further analysis on the cause of failure is still on-going and DPWH Region 2 has requested experts from the Bureau of Design and Bureau of Construction in the Central Office to conduct further evaluation and assessment,” the DPWH said.
“Further analysis on the cause of failure is still on-going and DPWH Region 2 has requested experts from the Bureau of Design and Bureau of Construction in the Central Office to conduct further evaluation and assessment,” the DPWH said.
MDRRMO Cabagan
.jpg)
2 CONTRACTS IN 2 YEARS
2 CONTRACTS IN 2 YEARS
Copies of 2 DPWH contracts with R.D. Interior, Jr. Construction showed the firm is a single proprietorship with main office address in Tuguegarao City, Cagayan.
Copies of 2 DPWH contracts with R.D. Interior, Jr. Construction showed the firm is a single proprietorship with main office address in Tuguegarao City, Cagayan.
A May 24, 2023 contract between DPWH, represented by Office of the Regional Director OIC Reynaldo Alconcel, and the company showed the department had contracted R.D. Interior, Jr. Construction to finish retrofitting the bridge in 330 calendar days for P274 million.
A May 24, 2023 contract between DPWH, represented by Office of the Regional Director OIC Reynaldo Alconcel, and the company showed the department had contracted R.D. Interior, Jr. Construction to finish retrofitting the bridge in 330 calendar days for P274 million.
MDRRMO Cabagan

READ: MAY 24, 2023 contract between DPWH and RD Interior Junior Construction
READ: MAY 24, 2023 contract between DPWH and RD Interior Junior Construction
A second DPWH contract with the same company
A second DPWH contract with the same company
in May 28, 2024 showed the government tapping R.D. Interior, Jr. Construction to do more retrofitting work on the Cabagan-Sta. Maria Bridge for P115 million, to be completed in 180 days.
in May 28, 2024 showed the government tapping R.D. Interior, Jr. Construction to do more retrofitting work on the Cabagan-Sta. Maria Bridge for P115 million, to be completed in 180 days.
MDRRMO Cabagan

READ: May 28, 2024 contract between DPWH and RD Interior Junior Construction
READ: May 28, 2024 contract between DPWH and RD Interior Junior Construction